The majority of the work this week was done Monday - Wednesday, in preparation for the arrival of the cement trucks on Wednesday afternoon.
The piles of rocks that were in the driveway last week are now compacted into the spaces between the concrete blocks where before there was just dirt. Construction paper is placed over it, then rebar for extra strength.
The foundation is ready for concrete and so we just wait for the cement trucks to arrive.
The remainder of the week will be spent watering the concrete and keeping it cool as it slowly hardens.